Planning List (8692) report: General explanation
The standard report 'Planning List' shows the planned and spent time of all operations per resource per year per start week and end week.
Datasets
- Planning Operations | 299 | plnb
Dataset filter
- Planning operation is not completed and the operation is not outsourced
Manual filters
- Operation.Resource Operation: allows filtering by resource
- Week Start: allows filtering by start week
- Week End: allows filtering by end week
Parameters
- Date Determination: indicates whether the date determination should be based on the start week or the end week of the planning
Details
- None