- MKG5
In addition to production orders, calculations can also be scheduled.
- MKG5
An order is automatically planned forward when no delivery date is entered. The end date is calculated based on the number of days from today during which planning is not allowed—according to the administration setting 'For planning ahead, start planning after'—plus the lead time in the schedule.